Groundworks and services installation for a 4,000 sqft Huf Haus project

  • Excavation for a 4m deep base
  • Slab preparation
  • Hard core areas for house building cran
  • Directional drilling for surface water pipe (180mm) and road crossing for SWW water supply
  • Installation of electrical ducting, water pipe, foul drainage pipe and BT ducting