Case Study Cheale Farm, Essex

Major infrastructure project to commercial farm

Works included:

  • UTX directional drilling of 125 mm gas main under Network Rail line and industrial compound together with connection to the national gas main;
  • Directional drilling under main road;
  • Lay 125mm gas main to include electro fusion joints and pressure testing;
  • Supply and installation of temporary concrete base and short term gas supply (Flogas) before main gas change over;
  • Construction of hard core access track.