Case Study Huf Haus, Ross-on-Wye

Demolition and Groundworks package for a Huf Haus new build – Principal Contractor

  • Demolition of existing bungalow including safe handling and disposal of asbestos
  • Setting out of site
  • Excavation of site and backfill with compacted Type 1 – CBR tested
  • Installation of surface water and foul drainage
  • Installation of ducting and air source heat pump pipework
  • Installation of slab reinforcement and slab pour
  • Stoning up of site for handover to Huf Haus build team