Case Study North Aller

Groundworks package for a new industrial estate in South Molton, Devon, with three steel frame buildings, onsite parking and a total of up to nine individual units.

  • Principle Contractor role
  • Cut and fill program
  • Installation of all drainage and utility services, inclusive of Klargester, Oil Seperator and attenuation pond
  • Slab construction to a power float finish
  • Installation of concrete road
  • Construction of gabion basket retaining wall
  • External landscaping of site