Case Study The Horses Trust, Speen

Groundworks package for large scale extension to Trust buildings

  • Cut and fill program for new manege / tractor storage building
  • Design and installation of new floor slabs and aprons
  • Installation of new road / track
  • Installation of surface water and foul water systems inc. attenuation and treatment plant
  • Directional drilling of over 200m of electrical ducting
  • Demolition of building and safe disposal of ACM’s
  • Fabrication and erection of new archive and indoor manege building including roof and cladding
  • Remediation and creation of new sand school inc. drainage and surface installation

Related case studies

Natsley Farm, Brayford

Cut and Fill marsh valley area below Natsley Farm house to create a large pond, Lined with Sodium Bentonite geotextile membrane Outfall pipe 300mm twin wall pipe

Dunheved Road, Launceston

Retaining wall stabilisation with use of platypus anchors Excavate 35m trench

Huf Haus, Ross-on-Wye

Huf Haus, Ross-on-Wye

Demolition and Groundworks package for a Huf Haus new build – Principal Contractor Demolition of existing bungalow including safe handling and disposal of asbestos Setting out of site Excavation of site and backfill with compacted Type 1 – CBR tested Installation of surface water and foul drainage Installation of ducting and air source heat pump… Read more »

Mapperton House, Dorset

Groundworks for a renewable energy project at a historic Grade I listed house and 5 estate properties together with the construction of a new access road. Works included: Groundworks and preparation of site for Biomass boiler and woodchip storage building together with auger woodchip delivery system;   Trenching and directional drilling for installation of Rehau insulated pipework and ducting;… Read more »

Mole Bridge, South Molton

The original bridge was hit with extensive flood damage. Demolition of original bridge and rebuild keeping the traditional features.